2
Grouted Installation: Carefully place first tile
(Figure 1) at the junction of the center marks.
Place two spacers on each side of the tile. Make
sure each tile is tight against your mark and
lightly butting the adjoining spacers.
Grout-less Installation: Carefully place first
tile at the junction of the center marks. Butt
additional tiles tight to adjoining tiles.
(Figure 1) (Figure 2)
Be sure the tile is well seated into the
adhesive. The tiles should be laid in
the pyramid fashion. (Figure 2)
To fit partial tiles, lay the tile to be cut exactly
over the last full tile. Place another full tile
against the wall and mark where they overlap.
If installing grouted installations adjust the mark
for the thickness of the grout joint. Cut using a
straight edge and utility knife. Roll flooring both
directions using a 100 pound sectional floor
roller.
(Figure 3)
Grouted Installations Only: Grout the
floor with acrylic grout designed for solid
vinyl tile. Never use cement or Epoxy
grouts. Always follow grout manufacturers
written instructions.
(Figure 4)
The Manufacturer is represented by: EarthWerks
®
10850 Train Ct. Houston , Texas 77041-6208 U.S.A. Email: sales@earthwerks.com
INSTALLING EARTH WERKS® GROUTED LUXURY VINYL
Tile should always be inspected for any dye lot variations. The Manufacturer will not warrant that different dye lots
will match each other.
Best results are obtained by installing the tile from the center of the room. Measure and mark at the center of each
end wall. Connect these center points with a chalk line. Locate the center and establish a line at a right angle to the
existing line. Measure from the center to determine the width of the perimeter tiles. If installing grouted installations,
add the width of each grout line to the total. The size of the perimeter tiles should be at least 1/2 the size of the tile.
If not, adjust your original center marks to achieve equal sized perimeter tiles.
Apply ST 100 pressure sensitive adhesive using a 1/16” x 1/16” x 1/16” square-notched trowel to 1/2 of the room. Allow
adhesive open time so it can dry to the touch. Tack time will vary depending upon temperature and humidity, and you will
also observe the color change from white to clear. Observing this open time is very important to ensure proper bonding
and to prevent possible bleed through. Begin installing the tile from the center of the room at the right angle marks. If
installing as a grouted installations, place two spacers along each tile edge and install the next tile gently against the
spacers. If installing without grout, make sure tiles are tight against the adjoining tile. Continue this until all the field tiles
are installed. Apply adhesive to the other 1/2 of the room. Finish making all perimeter cuts while the adhesive flashes.
Finish the second 1/2 of the room in the same fashion. Roll the whole floor with a 100 pound sectional roller. If installing as
a grouted installation use an acrylic grout designed for solid vinyl tile. Never use cement or Epoxy grouts. Always follow
grout manufacturers written instructions.
Note: Contact EarthWerks
®
for a list of other approved adhesives. www.earthwerks.com.
Note: Can be laid at a 45 degree angle. For more detailed instructions, contact EarthWerks
®
Technical
Department at 1-800-275-7943 Ext 8, 129.
If you are in the U.K. or Europe, you may also use F44/F46 by F. Ball & Co. Ltd., UK. Trowel size and usage
recommendations are stated on the pails of adhesive, and are also available from F. Ball & Co. Ltd., UK.
EarthWerks
®
Over Radiant Heat
EarthWerks
®
Flooring can be installed over radiant heat if the following guidelines are followed. Complete system must be
operational for a minimum of one week. System should be turned off 72 hours prior to installation of EarthWerks
®
flooring and
remain off 72 hours after installation is complete. Turn system back on to its normal room temperature setting. The subfloor
surface must never exceed 80 degrees Fahrenheit throughout the life of the floor. Flooring and adhesive should never come
in direct contact with heating system. All other standard installation instructions apply.
Last updated: 12•16•2014 • EarthWerks
®
Vinyl Tile Flooring • Installation Instructions